Kadina CBD Redevelopment

Kadina CBD Redevelopment

Implementation Phase

Construction of stage 1 will begin on the 21st of November 2016.

 

Stage 1 consists of stormwater pipework across the town centre and the upgrade of Frances Tce. This will prepare the town for stage 2 which will be implemented in 2017.

 

Stage 1 will pause from the 16th of December to the 11th of January to allow for the Christmas trading period. The aim is to have stage 1 completed in May 2017.

 

To remind our residents that Kadina will be open for business during the construction period, weekly prizes will be available for shoppers in the redevelopment zone. For details visit a participating store in the Kadina CBD

 

Current Works
Anticipated Start Date
Anticipated End Date
Stage and Location
Description of Works
21/11/2016 6/3/2017 2 - Frances Terrace (Western End) Stormwater & Carpark Works
 Temporary Road Closures

As Part of the Kadina CBD Redevelopment temporary road closures are required to provide a safe working environment for both the construction crew and public.

To enable the initial stages of the project, that being the Frances Terrace car park construction. It is Unique Urban Built's intention to provide a lane closer to Frances Terrace at Digby Street Monday 6 and Tuesday 7 February 2017. It is expected that works will be completed on Tuesday 8 February for this section of Work.

Unique Urban Built will commence works along Digby Street starting Monday 13 February 2017 with staged road closures as the works are carried out.


Unfortunately, this may create some inconvenience in the short term while works are being carried out.

Every effort will be made to minimise any disruptions.

Should you require any further information and or consultation please contact Unique Urban Built on 0439 015 892.


 

As Part of the Kadina CBD Redevelopment temporary road closures are required to provide a safe working environment for both the construction crew and public.
 
To enable the initial stages of the project, that being the Frances Terrace car park construction. It is Unique Urban Built's intention to close Frances Terrace from Day Street through to Hallett Street starting Monday 16th January 2017. The eastern section of Frances Terrace will remain open throughout this first stage to ensure car parking options are available.
 
Unfortunately, this may create some inconvenience in the short term while works are being carried out.
 
Every effort will be made to minimise any disruptions.
 
Should you require any further information and or consultation please contact Unique Urban Built on 0439 015 892.

 
 Next Stages
Anticipated Start Date
Anticipated End Date
Stage and Location
Description of Works
16/1/2017 15/3/2017 1A, 1B, 4A, B, C, D - Digby Street Stormwater Works in Digby Street
15/3/2017 11/4/2017 5A, 5B, 5C - Goyder Street Stormwater Works in Goyder Street
6/3/2017 22/5/2017 3 - Frances Terrace (Eastern End) Stormwater & Carpark works

 

Project Details

For all the information regarding this project, including frequently asked questions, and feedback and submission forms please click here.

 

For a plan of the design (June 2016), please  click here .

 

For a project implementation plan, please  click here .

 

For a project staging plan, please click here.

 

Background

In the 2014/15 Annual Business Plan the Council committed to the redevelopment of the Kadina Town Centre.

The area has been identified as the commercial hub for the Yorke Peninsula, but currently has a number of issues including;

  • Ageing infrastructure
  • Disability access
  • Pedestrian movements and safety
  • Shade and general amenity
  • Mismatch of pavement surfaces
  • Traffic flow and management

A master plan was created following public consultation in 2012/13.

Work is currently starting on the design and construction phase of the redevelopment with the project to be rolled out over 3 budget cycles. The 1st year (14/15) will include undertaking a trial in a short section of Graves Street that will provide the community an opportunity to contribute to the final designs. The trial will include the addition of trees into the CBD and the alteration of the pedestrian access and central crossing points.

The master plan suggested that a section of Graves Street be upgraded to introduce a shared use mall within the heart of the town centre, between Hallett and Goyder Streets. The intent of the shared use mall is to once again establish Kadina as not only the main service town within the Copper Coast but to help create a new identity for the town drawing locals and tourists to visit and spend time. A shared use mall would cater for parking opportunities directly to the front of shops and encourage social interactions strengthening community pride in Kadina.

The intent of the trial was to seek further community comment on this change, before the final construction plans were prepared.

 

Quick Links
District Council of the Copper Coast
51 Taylor Street
PO Box 396
Kadina SA 5554
Navigation