Moonta, Moonta Bay & Pt Hughes

Background

On 19th January 2005 Council appointed Kellogg Brown and Root (KBR) for the purpose of designing, calling tenders and supervising the construction of a Community Wastewater Management Scheme (CWMS) for Moonta, Moonta Bay and Port Hughes.

As a result of the meeting on 5th March 2008 KBR were released from this contract and replaced with a consortium of consultants in conjunction with the LGA consisting of Tonkins, Wallbridge and Gilbert and HDS to complete the design and documentation of the Moonta, Moonta Bay and Port Hughes CWMS.

Public Consultation

The Council has undertaken Public Consultation in relation to the Moonta, Moonta Bay and Port Hughes CWMS as required under the Local Government Act 1999, to ensure the community was aware of what is occuring. The District Council of the Copper Coast has undertaken the following:

1. 2012-2017 Project

CWMS Letter to residents 11th May 2012(230 kb)

CWMS Moonta, Moonta Bay, Port Hughes July 2012 Information(634 kb)

Moonta, Moonta Bay, Port Hughes CWMS Drainage Project Costs 2012(201 kb)

Council Meeting 3rd October 2012 - CWMS Easements(1318 kb)

Letter to Residents 29th May 2014(185 kb)

Connecting to CWMS - Moonta, Moonta Bay & Port Hughes(135 kb)
2. Stage 1 Construction Updates

  Moonta CWMS Summary Report - March 2013(1212 kb)

CWMS Project Update - March 2013(362 kb)

CWMS Project Update - April 2013(378 kb)

CWMS Project Update - May 2013(472 kb)

CWMS Project Update - June 2013(396 kb)

CWMS Project Update - July 2013(289 kb)

CWMS Project Update - August 2013(404 kb)

CWMS Project Update September 2013

CWMS Project Update - October 2013(571 kb)

CWMS Live Connections October 2013(95 kb)

CWMS Project Update - November 2013(475 kb)

CWMS Project Update - December 2013(460 kb)

CWMS Project Update - January 2014(378 kb)

CWMS Project Update - February 2014(397 kb)

CWMS Project Update March 2014(476 kb)

CWMS Project Update April 2014(508 kb)

CWMS Project Update - May 2014(500 kb)

CWMS Project Update June 2014(570 kb)

CWMS Project Update - July 2014(511 kb)

CWMS Project Update August 2014(463 kb)

CWMS Project Update - September 2014(641 kb)

Temporary Road Closures - Moonta Bay & Port Hughes

The District Council of the Copper Coast and CME Civil would like to advise the roads between Rossiters Road, Simms Cove Road and Coast Road Moonta Bay (as per the attached map) including Trelawney Street, Tipara Court, Gulf Street, Queens Place, Francis Place, Plymouth Street, Moontana Street and Moontana Avenue will incur temporary road closures. This is due to construction works on the Community Wastewater Management Scheme (CWMS). The roads will remain open to local traffic only. We apologise for any inconvenience this may cause.

Temporary Road Closures Moonta Bay & Port Hughes(186 kb)

3. Stage One Design Drawings

The stage 1 designs have now been completed and are available for viewing. Please view the overview plan first as this will assist you with locating your property on the actual design plans C02 – C09. There are two sets of design plans. The set with photos are much larger files and will take longer to download. If you would like to discuss any aspect of the project concerning your property please contact the office and we will be happy to assist you.

CWMS Stage 1 Plans For Construction 01

CWMS Stage 1 Plans For Construction 02

CWMS Stage 1 Plans For Construction 03

CWMS Stage 1 Plans For Construction 04

CWMS Stage 1 Plans For Construction 05

CWMS Stage 1 Plans For Construction 06

CWMS Stage 1 Plans For Construction 07

CWMS Stage 1 Plans For Construction 08

CWMS Stage 1 Plans For Construction 09

4. Previous Information

Geotechnical Investigation Report

Capital Costs

CWMS Public Consultation Report

Addendum to Public Consultation Document

Overall Scheme Layout

19 September 2006 - Public Meeting held at Moonta Town Hall

CWMS Postponement of Connection Fee Policy Report April 2010

Postponement of Connection Fee Policy - CWMS

CWMS Update May 09 CWMS%20Update (33 kb)

CWMS Easement Acquisition May 09

Kadina Wallaroo Audit Report Nov 2004

Appointment of KBR & Report Jan 2005

Audit Results Implemented

11th October 2006 - Special Council Meeting

1st August 2007 - General Manager's Report - IES Committee Agenda

6th February 2008 - Acting General Manager's Report - IES Agenda

7th May 2008 - General Manager's Report - IES Agenda

6th August 2008 - General Manager's Report - Council Agenda

Weather
Copper Coast
Top of page
51 Taylor Street, Kadina SA 5554 | Phone: (08) 8828 1200 | Fax: (08) 8821 2736 | Email: info@coppercoast.sa.gov.au
Navigation